Decision N° 2013-DC-0347 by the ASN of 7 May 2013

Published on 28/02/2014

ASN statutory resolutions

Decision N°. 2013-DC-0347 by the French Nuclear Safety Authority of 7 May 2013 setting out requirements to be met by Électricité de France – Société anonyme (EDF SA) at Flamanville nuclear site (Manche) for the Flamanville 3 reactor (INB No. 167) commissioning tests, amending Decision N°. 2008-DC-0114 by the French Nuclear Safety Authority setting out specific requirements to be met by Électricité de France – Société anonyme (EDF-SA) at the Flamanville nuclear site regarding the design and construction of the Flamanville-3 (INB No. 167) reactor and the operation of Flamanville-1 (INB No. 108) and Flamanville-2 (INB No. 109) reactors

ASN+Decision+2013-DC-0347+of+7+May+2013+FLA3+commissioning+tests+EN.pdf (PDF - 149.02 Ko )
Date of last update : 03/09/2021

This decision modifies / repeals the following decision:

Published on 28/02/2014

ASN STATUTORY RESOLUTIONS

Decision N° 2008-DC-0114 by the ASN of 26 September 2008

Decision No. 2008-DC-0114 of 26 September 2008 by the French Nuclear Safety Authority setting Forth Specific Requirementsto Be Met by Électricité de France – Société anonyme (EDF-SA) at the Flamanville Nuclear site Regarding the Design and Construction of the Flamanville-3 (INB No. 167) NPPand the Operation of Flamanville-1 (INB No. 108) and Flamanville-2 (INB No. 109) NPPs